How to advance sustainable development
Participate in Rio+Solutions, a global conversation about the key challenges expected to feature prominently at Rio+20, the United Nations Conference on Sustainable Development June 20-22, 2012.
Società Italiana di Monitoraggio S.p.A GICO Branch | Apply By 28 January 2010
TERMS OF REFERENCE
Formulation of the 10th EDF NAO Support Programme, phase III
EUROPEAID/127054/C/SV/multi
LOT N° X: REQUEST N° 2010/230039
The Government of Nigeria is currently implementing institutional and economic reforms through poverty reduction strategies such as Vision 2020, National Development Plan (NDP) and State Development Plan (SDP), at both federal and state level respectively. The European Union supports these reforms of the Government through the current 9th European Development Fund (EDF) and 10th EDF, but the implementation of this support has been hampered by a lack of capacity on behalf of the National Planning Commission (NPC) to manage the disbursements of the EDF efficiently. In this regard, NPC faces serious constraints in several areas such as technical expertise, internal control systems and monitoring and evaluation capabilities. Lessons learnt from the implementation of the 9th EDF also demonstrate lack of effectiveness in project coordination from the NPC, and Ministries, Departments and Agencies (MDAs) should play a more important role in the execution of projects.
The support to the office of the NAO programme, which started in 2004 (phase I) and continued its activities in 2008 (phase II), is the specific mechanism to address two main problems: the weak institutional and management capacity of the NPC to manage EDF funds and the lack of ownership of NPC in the coordination, management and evaluation of all external Official Development Assistance (ODA). Therefore, this programme foresees to improve the quality and impact of not only EDF funded projects in Nigeria but also the external aid of other donors, which may also benefit other departments of the federal and state levels of government.
DESCRIPTION OF THE ASSIGNMENT
The overall objective of this assignment is to support the Government of Nigeria in the formulation of the Support to the office of the NAO programme, phase III.
The specific objective of this assignment is to produce a complete set of project documents for the EC intervention within the scope of the 10th EDF National Indicative Programme for Nigeria.
The Specific tasks can be summarised as follows:
18. Prepare ToR for any service contract (Policy advise, Technical Cooperation, Capacity Development, Technical Assistance) to be involved in project implementation.
Methodology
The formulation will be done following the steps below:
1. The experts will carry out desk study of the relevant documents at the beginning of the mission. These documents will be provided to them at the beginning of the assignment. The experts will take into account the remarks, comments and suggestions of the QSGI (foreseen by early February 2010) when carrying out their mission.
2. A briefing meeting with the EU Delegation will be organised.
2. A kick-off meeting will be organised with the NPC and the consultants. In this meeting the experts will present the project to the participants and a general discussion will follow.
3. Several bilateral meetings with the relevant stakeholders will be organised by the experts in order to fully capture the needs of the beneficiaries and the best way to translate them into activities. This will include the stakeholders identified in the PIF.
4. A consultative meeting will be organised with the NPC and relevant stakeholders where the experts will present the findings of the mission and the participants will discuss and validate them.
5. A debriefing session will be organised at the end of the mission to inform the EU Delegation on the main findings and the steps forward for the finalisation and delivery of the outputs.
The experts will work in close and regular contact with the EU Delegation during their mission and will immediately raise any important issue to the EU Delegation, if any. The experts will conduct the necessary interviews and desk work as to ensure that the formulation documents are in line with the Government of Nigeria Priorities and that the project meets the quality standards to be financed.
All the outputs and deliverables will be conducted fully in line with the provisions, methodologies and templates of the Project Cycle Management Guidelines (March 2004), the Backbone Strategy (2009), Institutional Assessment and Capacity Development (September 2005) and any other EU related methodology. Any other methodologies could be used if duly justified and as long as the quality expectations of the EU Delegation are met.
In case of serious discrepancies with the documents prepared during identification (PIF and Annexes) the experts will raise the issue to the EU Delegation immediately and will include a SWOT analysis and an exit strategy/corrective measures to be put in place.
The mission will produce the following results:
1. An analysis of the operational feasibility of the proposed project, including its relevance, efficiency, effectiveness and sustainability.
2. An institutional and organisational capacity assessment that will analyse the operational and absorption capacity of the National Planning Commission; assessing its structures, human resources, technical capacity, flexibility to recruit and deploy qualified personnel, willingness and commitment.
3. An Action Fiche (Financing Proposal) including the Technical and Administrative Provisions (TAPs) and the draft of the Financing Agreement. These documents must follow the format provided for projects implemented by EuropeAid, including a detailed budget, a plan of action and a logical framework. The Action Fiche produced will have to ensure that it responds adequately to the QSG II checklist for the formulation phase.
4. The Terms of Reference for the governance structure (Programme Management Committee) and the operational management (Programme Support Unit) needed and identified in the PIF. These ToRs should include all the details in terms of human, material and financial resources of these structures: number and competence of its personnel, technical expertise, administrative procedures and daily operation practices.
5. Analysis of the relevant cross-cutting issues, to be carried out line with the EU guidelines and methodologies (accountability of public funds).
3. EXPERTS PROFILE
Two experts are required for this assignment
| Number | Category | Workdays |
Expert 1 | 1 | Senior | 35 |
Expert 2 | 1 | Junior | 35 |
Total | 2 |
| 70 |
Team Leader - Public Institutions Specialist
Minimum required skills
Expert in institutional capacity
Minimum required skills
If needed evidence may be required of the above skills.
4. LOCATION AND DURATION
Planning: It is envisaged that the tasks of the consultants will be covered through a period of 35 calendar days for each expert. 30 working days will be needed in Nigeria, while the remaining will be in their home base. The NPC and the EU Delegation will assist in facilitating meetings with stakeholders
| Timing (weeks) | ||||||||
Tasks | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | Responsibility |
Briefing EU DEL | X |
|
|
|
|
|
|
| EC and consultants |
Kick off meeting | X |
|
|
|
|
|
|
| EC/NPC/other stakeholders and consultants |
Inception report | X |
|
|
|
|
|
|
| Consultants |
Bilateral meetings and visits |
| X | X | X |
|
|
|
| Consultants |
Consultative meeting |
|
|
|
| X |
|
|
| EC/NPC/other stakeholders and consultants |
Debriefing EU DEL
|
|
|
|
| X |
|
|
| Consultants |
Submission Draft final reports and documents |
|
|
|
|
| X |
|
| Consultants |
Comments on reports and other deliverables |
|
|
|
|
|
| X |
| EC/NPC/other stakeholders |
Submission of Final Report (home) |
|
|
|
|
|
|
| X | Consultants |
5. REPORTING
The consultant will be responsible for the following reports:
The formal reports will be subject to EU Delegation approval. Once the reports are submitted, the EU Delegation will indicate to the consultants its approval or indicate the necessary changes to the consultants in writing. The consultants will have 5 days after the receipt of the comments to make the necessary modifications and for submission of the final version of the reports. The EU Delegation on will indicate to the consultant in writing its acceptance of the final report and other deliverables submitted.
All draft documents and inception report to be submitted to the EU Delegation in electronic format by email. The Final programming documents and other reports are to be submitted in electronic format by email and in 3 paper copies. Electronic/email versions must be in standard computerized format: Microsoft Word and Excel files.
On the ground of the specific Council regulations governing the concerned EC external aid program, VAT and any other local taxes and duties are excluded from the Community financing
Documents for consultation
1. Comments from the QSG I (foreseen for early February 2010)
2. Template of the Action Fiche
3. Template of the Technical and Administrative provisions
4. PIF - Support to the Office of NAO, phase III (submitted to QSG December 2009)
5. Specific Sector documents and other relevant annexes included in the PIF
6. Checklist of the QSG II
7. Relevant EC guidelines
8. Any other documents relevant to the formulation
The Logframe should include project objectives, a set of activities for delivering each project output and resource/cost schedules.
Specific, Measurable, Achievable, Relevant and Time-bound (SMART) and Objectively Verifiable Indicators (OVI)
In terms of Technical cooperation, Capacity building and Supply of equipment and the related activities.
"Reforming Technical Cooperation and Project Implementation", "Making Technical Cooperation more Effective" and "Toolkit for Capacity Development" (March 2009).
Strengths, Weaknesses, Opportunities and Threats.