The specific objectives of this technical audit of the Rehabilitation of the Negril Waste Water Treatment Plant are twofold:
1) To verify the contractual validity of the works certified by the Supervisor at expiry of the Operational Implementation Period of the Financing Agreement, i.e 31/12/2011.
2) To assess the management of the implementation of the works in accordance with the requirements of the contract and widely acknowledged best practices in the supervision of works contracts.
One senior expert for 25 working days
Quantity surveyor (Category Senior) – 25 working days
The Commencement Date of the Consultant’s services is the date of arrival inJamaicaof the Consultant’s expert (foreseen in the first week of November 2012)
The total contract duration is 120 calendar days.